Work on the new Midway has begun.
Permits approved

A defining milestone—and a new beginning.

The marina redevelopment has cleared the permitting stage. Now the focus turns to construction sequencing, field coordination, and bringing the approved plan to life.

Milestones

Years of work. One green light.

We will keep this page focused on meaningful, confirmed movement—not speculation.

  1. 1984

    A marina takes shape

    The existing marina was originally authorized, beginning Midway's long relationship with Lake Norman.

  2. 2024–25

    A new concept is developed

    Survey, engineering, shoreline, dock, and upland plans were assembled for agency review.

  3. June 2025

    Application package submitted

    A redevelopment package was submitted to Duke Energy through the Lake Services process.

  4. Approved

    The project gets the green light

    The marina permits are approved, clearing a defining milestone for the long-awaited redevelopment.

  5. Now

    Site work is underway

    Trees are being cleared as work on the new marina begins. The marina will be built in two phases.

  6. Spring

    First new slips expected

    The beginning slips are expected to be ready by spring, with first option going to current members' approved boats.

  7. 2027

    Phase 1: docks G–K

    Phase 1 builds docks G through K and is expected to be finished in 2027.

  8. Next

    Phase 2: docks A–F

    Docks A through F follow in Phase 2, once Phase 1 is complete. We'll confirm timing as work advances.

Project updates

Follow the build from here.

Join the list for meaningful, verified updates as the approved project advances.